【正确答案:A】
根据题意,该项目财务净现值的计算过程如下:
FNPV=-400(P/F,10%,1)-1000(P/F,10%,2)-600(P/F,10%,3)+350(P/A,10%,7)(P/F,10%,3)+200(P/F,10%,10)
=-400x0.909-1000x0.826-600x0.751+350x4.868x0.751+200x0.386
=-283.45(万元)

【正确答案:A】
根据题意,该项目财务净现值的计算过程如下:
FNPV=-400(P/F,10%,1)-1000(P/F,10%,2)-600(P/F,10%,3)+350(P/A,10%,7)(P/F,10%,3)+200(P/F,10%,10)
=-400x0.909-1000x0.826-600x0.751+350x4.868x0.751+200x0.386
=-283.45(万元)